Qualification tests of the national turbodiesel engine PD170 have been completed.

13 engines to be used in ANKA S / IHA will be delivered to TUSAS by the end of December 2019.

 



TEI General Manager Prof. Mahmut AKSIT's highlights:

- BAYKAR AKINCI's engine works continue. As soon as it's completed, we're going to produce a powerful engine without increasing the size. It will be the first in the world in this type of engine.

- We completed the jet engine core 2 years ago. We've gone through hundreds of tests, learned a lot. We reduced fuel consumption by half and increased power.

- 1500shp turboshaft engine manufacturing phase is over and assembly phase is started. We will deliver it for use in GOKBEY utulity helicopter within a year but engine maturation tests will continue.

- We will design bigger and more powerful jet engines.

- We have developed our own engineering software and library.


And it's worth remembering:

TEI has already built a NADCAP certified material testing laboratory and is currently conducting material testing to create its own material library. Thanks to this laboratory, TEI will save approximately 70 million dollars each year. In addition, no one in the world shares their material library with anyone.

tei tei.jpg


In addition to all, TEI is currently building a turboshaft engine R&D and test center to test all sub-components of a jet engine separately.

tei-test.jpg
 
التعديل الأخير:



TEI General Manager Prof. Mahmut AKSIT's highlights:

- BAYKAR AKINCI's engine works continue. As soon as it's completed, we're going to produce a powerful engine without increasing the size. It will be the first in the world in this type of engine.

- We completed the jet engine core 2 years ago. We've gone through hundreds of tests, learned a lot. We reduced fuel consumption by half and increased power.

- 1500shp turboshaft engine manufacturing phase is over and assembly phase is started. We will deliver it for use in GOKBEY utulity helicopter within a year but engine maturation tests will continue.

- We will design bigger and more powerful jet engines.

- We have developed our own engineering software and library.


And it's worth remembering:

TEI has already built a NADCAP certified material testing laboratory and is currently conducting material testing to create its own material library. Thanks to this laboratory, TEI will save approximately 70 million dollars each year. In addition, no one in the world shares their material library with anyone.

مشاهدة المرفق 219703

In addition to all, TEI is currently building a turboshaft engine R&D and test center to test all sub-components of a jet engine separately.

مشاهدة المرفق 219704

السلام عليكم ورحمة الله
عودا حميدا اخي الفاضل. Muhammed Fatih @Muhammed Fatih
شكرا علي المقال
ممكن استفسار
ايهما اصعب في التصنيع
١- turboshaft engine
٢- turbojet engine
 
السلام عليكم ورحمة الله
عودا حميدا اخي الفاضل. Muhammed Fatih @Muhammed Fatih
شكرا علي المقال
ممكن استفسار
ايهما اصعب في التصنيع
١- turboshaft engine
٢- turbojet engine

After developing the turbojet core engine, you can develop all the other engines through it. The most important part is to develop a turbojet core engine. TEI will develop turboshaft, turboprop and turbofan engines through this turbojet core engine.
 
After developing the turbojet core engine, you can develop all the other engines through it. The most important part is to develop a turbojet core engine. TEI will develop turboshaft, turboprop and turbofan engines through this turbojet core engine.
شاكر لكم اخي Muhammed Fatih @Muhammed Fatih علي ردكم
ولكن لدي سؤال آخر
هل بذلك ستكون تركيا من ضمن الدول المصنعة بالكامل للمحركات المختلفة للطائرات ام سيكون هناك اجزاء سيتم شرائها من الخارج
وشكرا لكم مرة أخرى
 
شاكر لكم اخي Muhammed Fatih @Muhammed Fatih علي ردكم
ولكن لدي سؤال آخر
هل بذلك ستكون تركيا من ضمن الدول المصنعة بالكامل للمحركات المختلفة للطائرات ام سيكون هناك اجزاء سيتم شرائها من الخارج
وشكرا لكم مرة أخرى

tei-ts1400.jpg


If all critical parts of this engine had not been developed and manufactured in Turkey, this engine would not be running for testing at this time. Because TEI General Manager Mahmut Aksit said that even Ukraine refused to (just) cast turbine blades for this engine. Of course, then this technology was developed in Turkey by TUBITAK MAM and casting was made by GURMETAL.

Long story short, no one in the world shares any critical technology with you. You have to develop all the critical technologies and production methods yourself. If you fail, you always depend on the outside and you can't be independent.
 
السلام عليكم ورحمة الله
انا عندي سؤال لو سمحتم
هي تركيا شغالة علي 3 محركات للدرونات الجديدة ( تقريبا اقنجي & اكسنجور )
واحد بالتعاون مع الأكران
والتاني بتاع بيرقدار ماكينا ( تحت الاختبار من 6 اشهر تقريبا )
والاخير من T.E.I " PD 170 "
انا في حاجة مش فاهما ولا الكلام ده صح ؟
Muhammed Fatih @Muhammed Fatih
Amr Ghoniem @amrrr10
عثماني @عثماني
salem1520 @salem1520
L @larbi
 
AKINCI Block-1 (2 x TEI PD-220 Turbodiesel engine)
AKINCI Block-2 (2 x TEI TP-550 Turboprop engine)
السلام عليكم اخي Muhammed Fatih @Muhammed Fatih
كيف حالك
أعتقد أن هذا الكلام قد اختلف الان مع وجود
محرك من بايكار ماكينا و محرك بالتعاون مع أوكرانيا
ام لازالت نفس الخطة قائمة ؟
شكرا لكم
 
السلام عليكم ورحمة الله
انا عندي سؤال لو سمحتم
هي تركيا شغالة علي 3 محركات للدرونات الجديدة ( تقريبا اقنجي & اكسنجور )
واحد بالتعاون مع الأكران
والتاني بتاع بيرقدار ماكينا ( تحت الاختبار من 6 اشهر تقريبا )
والاخير من T.E.I " PD 170 "
انا في حاجة مش فاهما ولا الكلام ده صح ؟
Muhammed Fatih @Muhammed Fatih
Amr Ghoniem @amrrr10
عثماني @عثماني
salem1520 @salem1520
L @larbi
اخي مشروع PD170 جاهز
 
السلام عليكم ورحمة الله
انا عندي سؤال لو سمحتم
هي تركيا شغالة علي 3 محركات للدرونات الجديدة ( تقريبا اقنجي & اكسنجور )
واحد بالتعاون مع الأكران
والتاني بتاع بيرقدار ماكينا ( تحت الاختبار من 6 اشهر تقريبا )
والاخير من T.E.I " PD 170 "
انا في حاجة مش فاهما ولا الكلام ده صح ؟
Muhammed Fatih @Muhammed Fatih
Amr Ghoniem @amrrr10
عثماني @عثماني
salem1520 @salem1520
L @larbi

نفس المعلومه عندي ولا يوجد جديد الا لو الاعضاء المحترمين اضافو شي
 
عودة
أعلى