مصر بين الواقع و الخيال ( موضوع للمناقشه ) ؟؟

الحالة
مغلق و غير مفتوح للمزيد من الردود.
رد: مصر بين الواقع و الخيال ( موضوع للمناقشه ) ؟؟

Yes not happen but all world speak about it
ha ha ha ha ha ha ha ha ha
zenawi10.jpg

http://www.biyokulule.com/Zenawi5.jpg
And the foolish DUMB man Meles' dam went "sAnd the foolish DUMB man Meles' dam went "splat!"
plat!"


Gilgel Gibe collapses 2 wks after inauguration
Ethiopia's Hydro Plans Get Stuck in the Mu
http://www.internationalrivers.org/files/images/GG2 inauguration.jpg

Meles Zenawi and Italy's Foreign Minister inaugurate Gilgel Gibe 2
On Jan. 13, Ethiopia's Prime Minister Meles Zenawi inaugurated the Gilgel Gibe 2 scheme, the country's biggest hydropower project. "It is possible to speed up development without polluting the environment," Zenawi proudly declared as he cut the ceremonial ribbon. Yet this was wishful thinking.

Due to shoddy preparation, the project had already been delayed by more than two years. And less than two weeks after the inauguration, the project's core component, a 26 kilometer-long tunnel, collapsed partly. Power generation had to be stopped for several months. Ethiopia's hydro sector demonstrates that there are not shortcuts to sound infrastructure development. Cutting corners does not "speed up development," but produces costly mistakes.

Gilgel Gibe 2 has a price tag of 374 million Euros and a capacity of 420 megawatts. The project works without a reservoir, but channels the water discharged from the Gilgel Gibe 1 Dam through a long tunnel and a steep drop directly to the valley of the Omo River. The undertaking was plagued by shoddy management from the beginning. In violation of Ethiopian law, the government negotiated the project contract with the Italian construction company Salini without competitive bidding. No-bid contracts for public works projects are a big red flag of corruption. The Gilgel Gibe deal was awarded without a feasibility study, and construction started without the legally required environmental permit.

In violation of Italian law and against the recommendation of its own evaluators, Italy's Ministry of Development Cooperation awarded 220 million Euros of aid money for Salini's no-bid contract. Gilgel Gibe 2 was "the biggest development fund released to a single project in the history of the Italian Cooperation," the Ministry says proudly. The European Investment Bank, which is notoriously weak in appraising power projects, contributed another 50 million Euros, and the Ethiopian government funded the remaining 104 million Euros.

Gilgel Gibe 2 construction site (www.itacaddis.org)
Gilgel Gibe 2 was supposed to be completed in Dec. 2007. Yet the poor preparation soon took its toll. Deficient geological studies had overlooked sandy soils and aquifers in the rock. The tunnel boring equipment got stuck in the mud, and the engineers had to redesign the tunnel's path. As we heard, the aqueduct collapsed only 12 days after its inauguration, nine kilometers inside the mountain.

Who pays the price for such development failures? The dubiously negotiated contract for Gilgel Gibe 2 exempts Salini from geological risks, so the Ethiopian electricity consumers and tax payers ended up paying for the cost-overruns. Salini will certainly try to shift the blame for the tunnel collapse to Ethiopia once again. In the meantime, the country's poor remain without electricity, and the environment gets spoilt for nothing.
Italy's Campagna per la Riforma della Banca Mondiale has documented the numerous legal problems and shortcuts of the Gilgel Gibe 2 project in detail. The Campagna's Caterina Amicucci comments that aid projects like Gilgel Gibe 2 "not so much address a country's urgent development needs, but subsidizes a major Italian company." The Campagna and International Rivers have asked that the bill for the latest disaster be paid by Salini and not Ethiopia's taxpayers.

Gilgel Gibe 2's dodgy deal is the rule, not the exception in Ethiopia's hydropower sector. The contract for the slightly smaller Tekeze Dam was awarded in 2002, and power generation was supposed to start in 2007. Yet in this case, the ground on which the dam was being built was too weak -- a fact which a proper feasibility study would have found in advance. Landslides caused further delays, and the project was commissioned two years late in 2009.
The story doesn't end with Gilgel Gibe 2 and Tekeze. In July 2006, the government awarded a $2.1 billion contract for the Gibe 3 Dam -- its biggest infrastructure project ever -- to Salini through direct negotiations. Again there was no competitive bidding. Again project construction started without an Environmental Impact Assessment and an Economic, Financial and Technical Assessment. If built, the Gibe 3 Dam will devastate the fragile ecosystems of the Lower Omo Valley and Lake Turkana, on which 500,000 poor farmers, herders and fisherfolk rely for their livelihoods. Even though the project violates Ethiopian law and their own safeguard policies, the African Development Bank and the World Bank are currently considering support for the project.

Will the collapse of the Gilgel Gibe 2 be a wake-up call for the World Bank and the African Development Bank? Latest news indicates that the financiers, who refused to get involved in Gilgel Gibe 2, may yet shy away from the dodgy Gibe 3 deal. They know that their credibility is on the line.

http://www.internationalrivers.org/e...-get-stuck-mud


والنتيجة سيدفع المغفلون المزيد وسيجصدون الندم اينما ذهبوا
Gilgel Gibe II will take two months and will cost 356 million birr to repair

A collapse in a tunnel has forced the closure of Ethiopia’s largest hydropower plant, Gilgel Gibe II, one week after it was inaugurated. Engineers have estimated that the repairs will take two months and cost 356 million birr. As a result, large factories have been asked to halve their power consumption.

A week after it was officially inaugurated, the largest hydropower station in Ethiopia’s history, Gilgel Gibe II (GG II) has suffered a collapse of a section of a tunnel.

Minister of Mines and Energy Alemayehu Tegenu said that the plant halted operations on Sunday, January 24 after signs of a drop in pressure were observed. He said that the problem occurred some nine kilometres from the outlet of the tunnel and that 15 metres has collapsed.

Semegnew Bekele (Eng), GG II Project Manager, said the problem is easy to solve and could be fixed in a very short time.

The reconstruction work is expected to cost a maximum of 18 million Euros, (365 million birr) and take two months, according to engineers’ estimates. Reinforcement work is also expected to be done to strengthen other sections of the tunnel.

Engineers added that they think the costs of the repair work will be covered by the contractor, as it is liable for repair work for one year after completion of the project. The contractor for GG II was Italian firm, Salini Costruttori, which also constructed Gilgel Gibe I.

Factories that consume large amounts of electric power have been ordered by the Ethiopian Electric Power Corporation (EEPCo) to reduce their consumption by 50 per cent as a result of the incident.

Following Tekeze Hydropower Plant’s launch, the opening of GG II was the second of three major hydropower projects that were expected to come online this fiscal year.

GG II, which was constructed 250km south west of Addis Ababa for over 5.2 billion birr, can generate 420 megawatts of electricity from its four turbines. It was predicted that it was going to increase electric power supply by 38 per cent.

The Italian Government and the European Investment Bank paid for 52 per cent of the total cost, while the Ethiopian Government covered the balance.

GG II was supposed to solve the country’s power shortage and was also expected to export power to neighbouring countries.

Mihiret Debebe, CEO of EEPCo, said that the corporation is doing its best to solve the power shortage and is going to rapidly complete Beles Hydropower Project, which is expected to generate 460 mw when it starts operation in the next couple of weeks.

GG II, an extension of the Gilgel Gibe I (GG I) hydropower project, does not have a dam. Instead, it uses the water discharged by the GG I, channeled through a 26 km tunnel under Fofa mountain, to Omo River Valley where it takes advantage of a 1.2 km drop to generate 420 mw.

Construction of GG II was launched in 2005.


Also underway is the Gibe III hydropower project, which, when operational, will double the country’s power capacity by generating 1,870 mw. The project launched in March 2008 is expected to cost around 20 billion birr. The same Italian firm has so far completed about 35 percent of the civil works of the project at a slow pace due to financing problems


Gilgel Gibe II will take two months and will cost 356 million birr to repair
http://www.newsdire.com/news/print:...and-will-cost-356-million-birr-to-repair.html

 
رد: مصر بين الواقع و الخيال ( موضوع للمناقشه ) ؟؟

ممكن تلخيص للمقال ده
 
رد: مصر بين الواقع و الخيال ( موضوع للمناقشه ) ؟؟

شكرا جدا يا شباب علي التعليق مع ان اتمني ان يكون الكلام ده صحيح .. بس الواحد مش شايف حاجه من الكلام ده .. شكرا
 
رد: مصر بين الواقع و الخيال ( موضوع للمناقشه ) ؟؟

يا اخي الكريم elm3lam حب الوطن من الايمان والله يهدينا اجمعين فالذي قلته على بلادنا الشقيقة مصر ينطبق على كل بلدننا العربية وان عمت خفت
فتفال خيرا تجدوه ولن ينقطع الخير من امة محمد عليه افضل الصلاة وازكى السلام الى يوم الدين
 
رد: مصر بين الواقع و الخيال ( موضوع للمناقشه ) ؟؟

شكرا جدا يا شباب علي التعليق مع ان اتمني ان يكون الكلام ده صحيح .. بس الواحد مش شايف حاجه من الكلام ده .. شكرا

وهل اعطيت شيئا بالطبع لا فقط تريد ان تجد كل شىء ميسر وسهلا تعلمت مجانا حتى لو تعليم سيىء ماذا استفاد منك الوطن صفر تعيش على الدعم وتعالج سواء علاج سىء او جيد فى المستشفيات الحكومية ماذا اعطيت صفر وفى المقابل تسال لا ارى
وهل انت
قراءات او فهمت حتى تابعت الاخبار او انت متهم باى شأن غير
الذات هو ما تهتم به وبالطبع لن ترى فانت متقوقع فى نفسك وفى ذاتك كثير من الناس ذاتهم انفسهم فقط وحدهم فقط ماذا قدموا لاوطانهم لكى يسالوا المقابل لا شىء هل تستحق تلك النوعيات من البشر شىء بالطبع لا
يعجبنى الشاكين غير المنتتجين او ذى قيمة ويسالون المنح او الخير لذا حتى الاجابة ربما قيمتها اكبر بكثير من السؤال

 
رد: مصر بين الواقع و الخيال ( موضوع للمناقشه ) ؟؟

اخى الكريم لا تظلم جيش مصر وشعبها ولكن لابد ان تاخذ فى الحسبان ان هناك حروب نفسيه على مصر لكى تكون خانعه ولكن بعين محايده الدوله لاتبخل على القوات المسلحه بفدر الامكان فترى مثلا فى القوات الجويه الطيار المصرى حير العالم بخبرته وكذلك مصر لديها طائرات حديثه وقويه وسلاح طيران قوى جدا وكذلك الدفاع الجوى المصرى عريق وله خبرات وامكانات جيده جدا وعندما تقارن دوله مثل تركيا بمصر رغم ما وقع على مصر من عصور لم تكن تملك ارادتها وعند المقارنه بايران ستجد حال القوات المصريه جيده للغايه وهى على تقرير قد قراته صادر عن موقع فاس ان القوات الجويه المصريه اقوى من الايرانيه بمراحل ومن حيث الاقتصاد لاتنسى اننا خرجنا من عصر اقتصاد الحرب الى عصر نواجه فيه افاعى وحيات اقتصاديه تريد ابتلاعنا احياء ولكن اللله الحافظ من هذه الكايانات وعلى راسه اسرائيل
 
رد: مصر بين الواقع و الخيال ( موضوع للمناقشه ) ؟؟

Yes not happen but all world speak about it
ha ha ha ha ha ha ha ha ha
zenawi10.jpg

http://www.biyokulule.com/Zenawi5.jpg
And the foolish DUMB man Meles' dam went "sAnd the foolish DUMB man Meles' dam went "splat!"
plat!"


Gilgel Gibe collapses 2 wks after inauguration
Ethiopia's Hydro Plans Get Stuck in the Mu
http://www.internationalrivers.org/files/images/GG2%20inauguration.jpg

Meles Zenawi and Italy's Foreign Minister inaugurate Gilgel Gibe 2
On Jan. 13, Ethiopia's Prime Minister Meles Zenawi inaugurated the Gilgel Gibe 2 scheme, the country's biggest hydropower project. "It is possible to speed up development without polluting the environment," Zenawi proudly declared as he cut the ceremonial ribbon. Yet this was wishful thinking.

Due to shoddy preparation, the project had already been delayed by more than two years. And less than two weeks after the inauguration, the project's core component, a 26 kilometer-long tunnel, collapsed partly. Power generation had to be stopped for several months. Ethiopia's hydro sector demonstrates that there are not shortcuts to sound infrastructure development. Cutting corners does not "speed up development," but produces costly mistakes.

Gilgel Gibe 2 has a price tag of 374 million Euros and a capacity of 420 megawatts. The project works without a reservoir, but channels the water discharged from the Gilgel Gibe 1 Dam through a long tunnel and a steep drop directly to the valley of the Omo River. The undertaking was plagued by shoddy management from the beginning. In violation of Ethiopian law, the government negotiated the project contract with the Italian construction company Salini without competitive bidding. No-bid contracts for public works projects are a big red flag of corruption. The Gilgel Gibe deal was awarded without a feasibility study, and construction started without the legally required environmental permit.

In violation of Italian law and against the recommendation of its own evaluators, Italy's Ministry of Development Cooperation awarded 220 million Euros of aid money for Salini's no-bid contract. Gilgel Gibe 2 was "the biggest development fund released to a single project in the history of the Italian Cooperation," the Ministry says proudly. The European Investment Bank, which is notoriously weak in appraising power projects, contributed another 50 million Euros, and the Ethiopian government funded the remaining 104 million Euros.

Gilgel Gibe 2 construction site (www.itacaddis.org)
Gilgel Gibe 2 was supposed to be completed in Dec. 2007. Yet the poor preparation soon took its toll. Deficient geological studies had overlooked sandy soils and aquifers in the rock. The tunnel boring equipment got stuck in the mud, and the engineers had to redesign the tunnel's path. As we heard, the aqueduct collapsed only 12 days after its inauguration, nine kilometers inside the mountain.

Who pays the price for such development failures? The dubiously negotiated contract for Gilgel Gibe 2 exempts Salini from geological risks, so the Ethiopian electricity consumers and tax payers ended up paying for the cost-overruns. Salini will certainly try to shift the blame for the tunnel collapse to Ethiopia once again. In the meantime, the country's poor remain without electricity, and the environment gets spoilt for nothing.
Italy's Campagna per la Riforma della Banca Mondiale has documented the numerous legal problems and shortcuts of the Gilgel Gibe 2 project in detail. The Campagna's Caterina Amicucci comments that aid projects like Gilgel Gibe 2 "not so much address a country's urgent development needs, but subsidizes a major Italian company." The Campagna and International Rivers have asked that the bill for the latest disaster be paid by Salini and not Ethiopia's taxpayers.

Gilgel Gibe 2's dodgy deal is the rule, not the exception in Ethiopia's hydropower sector. The contract for the slightly smaller Tekeze Dam was awarded in 2002, and power generation was supposed to start in 2007. Yet in this case, the ground on which the dam was being built was too weak -- a fact which a proper feasibility study would have found in advance. Landslides caused further delays, and the project was commissioned two years late in 2009.
The story doesn't end with Gilgel Gibe 2 and Tekeze. In July 2006, the government awarded a $2.1 billion contract for the Gibe 3 Dam -- its biggest infrastructure project ever -- to Salini through direct negotiations. Again there was no competitive bidding. Again project construction started without an Environmental Impact Assessment and an Economic, Financial and Technical Assessment. If built, the Gibe 3 Dam will devastate the fragile ecosystems of the Lower Omo Valley and Lake Turkana, on which 500,000 poor farmers, herders and fisherfolk rely for their livelihoods. Even though the project violates Ethiopian law and their own safeguard policies, the African Development Bank and the World Bank are currently considering support for the project.

Will the collapse of the Gilgel Gibe 2 be a wake-up call for the World Bank and the African Development Bank? Latest news indicates that the financiers, who refused to get involved in Gilgel Gibe 2, may yet shy away from the dodgy Gibe 3 deal. They know that their credibility is on the line.

http://www.internationalrivers.org/e...-get-stuck-mud


والنتيجة سيدفع المغفلون المزيد وسيجصدون الندم اينما ذهبوا
Gilgel Gibe II will take two months and will cost 356 million birr to repair

A collapse in a tunnel has forced the closure of Ethiopia’s largest hydropower plant, Gilgel Gibe II, one week after it was inaugurated. Engineers have estimated that the repairs will take two months and cost 356 million birr. As a result, large factories have been asked to halve their power consumption.

A week after it was officially inaugurated, the largest hydropower station in Ethiopia’s history, Gilgel Gibe II (GG II) has suffered a collapse of a section of a tunnel.

Minister of Mines and Energy Alemayehu Tegenu said that the plant halted operations on Sunday, January 24 after signs of a drop in pressure were observed. He said that the problem occurred some nine kilometres from the outlet of the tunnel and that 15 metres has collapsed.

Semegnew Bekele (Eng), GG II Project Manager, said the problem is easy to solve and could be fixed in a very short time.

The reconstruction work is expected to cost a maximum of 18 million Euros, (365 million birr) and take two months, according to engineers’ estimates. Reinforcement work is also expected to be done to strengthen other sections of the tunnel.

Engineers added that they think the costs of the repair work will be covered by the contractor, as it is liable for repair work for one year after completion of the project. The contractor for GG II was Italian firm, Salini Costruttori, which also constructed Gilgel Gibe I.

Factories that consume large amounts of electric power have been ordered by the Ethiopian Electric Power Corporation (EEPCo) to reduce their consumption by 50 per cent as a result of the incident.

Following Tekeze Hydropower Plant’s launch, the opening of GG II was the second of three major hydropower projects that were expected to come online this fiscal year.

GG II, which was constructed 250km south west of Addis Ababa for over 5.2 billion birr, can generate 420 megawatts of electricity from its four turbines. It was predicted that it was going to increase electric power supply by 38 per cent.

The Italian Government and the European Investment Bank paid for 52 per cent of the total cost, while the Ethiopian Government covered the balance.

GG II was supposed to solve the country’s power shortage and was also expected to export power to neighbouring countries.

Mihiret Debebe, CEO of EEPCo, said that the corporation is doing its best to solve the power shortage and is going to rapidly complete Beles Hydropower Project, which is expected to generate 460 mw when it starts operation in the next couple of weeks.

GG II, an extension of the Gilgel Gibe I (GG I) hydropower project, does not have a dam. Instead, it uses the water discharged by the GG I, channeled through a 26 km tunnel under Fofa mountain, to Omo River Valley where it takes advantage of a 1.2 km drop to generate 420 mw.

Construction of GG II was launched in 2005.


Also underway is the Gibe III hydropower project, which, when operational, will double the country’s power capacity by generating 1,870 mw. The project launched in March 2008 is expected to cost around 20 billion birr. The same Italian firm has so far completed about 35 percent of the civil works of the project at a slow pace due to financing problems


Gilgel Gibe II will take two months and will cost 356 million birr to repair
http://www.newsdire.com/news/print:...and-will-cost-356-million-birr-to-repair.html


بصراحة الرد أفحمنى .. أنا الآن مفحوم
أرد فقط على الأخ الذى سأل متى حدث هذا
سد تيكيزى فى شمال أثيوبيا على نهر تيكيزى .. بينما Gilgel Gibe فى وسط أثيوبيا على نهر يحمل اسمه متفرع من نهر أومو النابع من بحيرة توركانا على الحدود الأثيوبية الكينية فى أقصى جنوب أثيوبيا
أى أن سد تيكيزى شئ و ما ذكر فى الرد المقتبس شئ آخر تماما
 
رد: مصر بين الواقع و الخيال ( موضوع للمناقشه ) ؟؟

ماشي بص يا سيدي هأتكلم معاك من وجهة نظري اولا بالنسبة لي الانهيارة الاقتصادي ده غير صحيح الدخل القومي المصري توجد ارقام تقول انه يتخطي 300 مليار وده رقم لا بأس به بالنسبة لي افريقيا والشرق الاوسط (لا امل للمقارنة مع الدول الاوربية ) بالنسبة لي الوضع السكري او وضع الجيش صحيح الجيش فيه وسطة بشكل كبير وفيه سرقة ولكن يوجد ايضا شخصيات شريفة ومحترمة جدااااااااااااااااااا داخل الجيش المصري وده شئ انا رأيته بعيني مش هاقولك بيحاربوا الفساد والوطن والكلام ده ولكن هاقولك انه فعلا بيحاولو يراعوا الله في عملهم بقدر المستطار وانهم بيجوا علي صحتهم الشخصية بشكل كبييييير فقد لي ارضاء الله وتحليل الاموال الي بيخدوها والي هي طبعااا مبالغ كبيييييرة مش هاقول لا ولكن فعلا يستحقوها عن جدارة بالنسبة لي نقطة التسليح واغلب الاسلحة قديمة لا اعلم عن اي جيش تتحدث احنا بنوشف بعينا الاسلحة المصرية في المناورات وبراجم طلائع النصر وحفلات الخرج وتظهر الاسلحة القديمة مع الحديثة ايضااا جايز الي بيقول كدا بيتكلم عن تجهيز المشاة العادية وهم بالفعل تجهيزهم وتسليحهم مقارنة بدول اخري مجاورة سئ ولكن في خطة لي تطوير المشاة سلاح وتجهيز (خوذات الكليفار دروع مضادة للرصاص استبدال البنادق المعادي القديمة بأخري احدث) ولكن لا تنسي ان عدد المشاة او الجنود عامة في الجيش المصري اكبر من اي جيش اخر في المنطقة لذا فتلك العملية هتأخذ وقت وراجع او اتفرج علي فيديوهات الجيش المصري في المناورات والتدريبات هتلاحظ انتشار الخوذة الكليفار بين فروع الجيش وايضا الدروع المضادة للرصاص المجندين من اصدقائك واصدقائي نعم بيشوفوا ايام صعبة وذل قهر ولكن يا اخي هؤلاء جنود واذا لم يتحملوا ايام صعبة تدريبا او وقفة ساعتين في الشمس فكيف هيتحملوا قذائف الفسفور الابيض من العدو في الحرب والتعذيب في لا قدر الله الاسر وبعدين اذا كان اصدقائك بيشتكوا من القهر والظلم في مراكز الجنيد حسب كلامهم اطلب منهم يسألوا الي بيحصل لي الجنود اثناء تدريبا فرقة الصاعقة او السيل (تدريبات غير ادامية) بالنسبة لي الوضع السياسي فنصيحة مني ما تتفرجش علي قناة الزريبة الشهيرة بالجزيرة لانها القناة الوحيدة المبنية علي سب مصر والنظام في مصر وتناسوا تماما القاعدة الموجودة في ارضهم بالنسبة لي موضوع المعابر فكلام الجزيرة غير صحيح المصابين كانو يدخلون وسيارات الاسعاف المصرية دخل القطاع وهناك اكتر من طبيب مصري اصيب وموضوع الانفاق الجميع عارف انه بعلم السلطات المصرية وانهم يسمحون بدخول الاسلحة عبرها وباقي البضائع فبغير المعقول وجود مئات الانفاق علي شريط حدودي ليس بالكبير ولا تعلم حرس الحدود عنه شئ (ياراجل دول لو موقفين كتاكيت كانو اخدو بالهم) النسبة لي موضوع الوزراء والفساد فده امر مسلم بيه ومعروف وجود فساااااااااااد كبيرة في المنظومة وسرقة ...الخ (ربنا يجعل كلامنا خفيف عليهم) بس برضه والله العظيم في ناس شرفاء وبيشتغلوا بجد بعيد عن الكلام ده وعموما السرقة مش في بلدنا بس موجودة في كل دول العالم وبشكل سافر اكتر من كدا ايضاااااا واكبر دليل امريكا ولكن الفرق انهم هناك يسرقوا بأحترافية اكبررر وبيقدرو يخفوا عمليات السرقة والنهب
فعلاً رائع فأنا مثلك خدمت كضابط إحتياط في القوات المسلحة المصرية ورأيت بعيني مدى كفاءة قواتنا المسلحة وأشهد أنها كانت أجمل ثلاث سنوات لي.
 
رد: مصر بين الواقع و الخيال ( موضوع للمناقشه ) ؟؟

شكرا اخي المقاتل
 
رد: مصر بين الواقع و الخيال ( موضوع للمناقشه ) ؟؟

وهل اعطيت شيئا بالطبع لا فقط تريد ان تجد كل شىء ميسر وسهلا تعلمت مجانا حتى لو تعليم سيىء ماذا استفاد منك الوطن صفر تعيش على الدعم وتعالج سواء علاج سىء او جيد فى المستشفيات الحكومية ماذا اعطيت صفر وفى المقابل تسال لا ارى
وهل انت
قراءات او فهمت حتى تابعت الاخبار او انت متهم باى شأن غير
الذات هو ما تهتم به وبالطبع لن ترى فانت متقوقع فى نفسك وفى ذاتك كثير من الناس ذاتهم انفسهم فقط وحدهم فقط ماذا قدموا لاوطانهم لكى يسالوا المقابل لا شىء هل تستحق تلك النوعيات من البشر شىء بالطبع لا
يعجبنى الشاكين غير المنتتجين او ذى قيمة ويسالون المنح او الخير لذا حتى الاجابة ربما قيمتها اكبر بكثير من السؤال


شكرا علي ردك .. اولا انا كتبت الموضوع علشان انا بحب مصر ليس اكتر وكان فكري مشتت بين الصح و الخطاء علشان كده كتبت الموضوع حتي اجد الاجابه من اعضاء المنتدي و ليس الهجوم عليه .. اما بلنسبه لي كلامك ماذا اعطيت لمصر ؟ ممكن اقولك ماذا اعطي الانسان لي ابوه و اموه حتي يعلموه و يجوزوه و يصرفه عليه عمره كله ؟ ماذا اعطا العبد الي الله حتي يرزقه الله بلمال و الولد ؟ فئذا ا ليس حق علي احد ان يقول مذا اعطي فولان لي دوله يعيش فيها لائن هذا واجب علي الدوله ان ترعي مصالح ابنئها و نحن لم نتظر من احد عطف او شفقه و لكن هذا حق مكتسب لكل فرد يعيش في دوله ؟ ده بلنسبه لكلامك اما موضوعي انا كنت عايز اجابه للتناقد الشديد الي موجود في مصر الان هل نحن مذلنا دوله اقلميه ليها ثقل سياسي حقيقي و منتبق مبداء ما خفي كان اعظم ام انها مجرد خرفات او ماضي او مجرد كلام ؟؟؟؟؟
شكراااااااا
 
رد: مصر بين الواقع و الخيال ( موضوع للمناقشه ) ؟؟

بصراحة الرد أفحمنى .. أنا الآن مفحوم
أرد فقط على الأخ الذى سأل متى حدث هذا
سد تيكيزى فى شمال أثيوبيا على نهر تيكيزى .. بينما gilgel gibe فى وسط أثيوبيا على نهر يحمل اسمه متفرع من نهر أومو النابع من بحيرة توركانا على الحدود الأثيوبية الكينية فى أقصى جنوب أثيوبيا
أى أن سد تيكيزى شئ و ما ذكر فى الرد المقتبس شئ آخر تماما

يا ريت يا د/جوهر تترجم المقال عشان نفهمه.
 
رد: مصر بين الواقع و الخيال ( موضوع للمناقشه ) ؟؟

باختصار ميليس زيناوى و وزير خارجية إيطاليا دشنوا فى 13 يناير مخططات مشروع لإقامة سد بهدف توليد الكهرباء على نهر اسمه Gilgel Gibe ( و كان هذا هو السد الثانى فقد سبق بناء سد على هذا النهر من قبل ) و بسبب سوء البنية التحتية فقد انهار النفق الذى يعد أساس المشروع انهيارا جزئيا مما أدى إلى تأخير موعد افتتاح المشروع لسنتين و ستبلغ تكلفة التصليحات 356 مليون birr ( يبدو أنها عملة أثيوبيا )

بعيدا عن المقال حتى نفهم المقصود .. تم بناء سد على نهر Gilgel Gibe لتوليد الكهرباء و تمر عبره المياه التى تعبر خلال النفق لتصل لمحطة توليد ثانية هى Gilgel Gibe II دون الحاجة لبناء سد آخر .. و ما انهار هو هذا النفق
أما سد تيكيزى فى شمال أثيوبيا فلم أقرأ شيئا عن انهياره .. اللهم إلا خبرا فى منتدى أثيوبى تحدث عن انهيار نفق بنفس مواصفات نفق Gilgel Gibe II و لم يتحدث عن سد تيكيزى إلا فى العنوان فقط و للأمانه فهذا رابطه http://www.ethiopianreview.com/forum/viewtopic.php?f=2&t=17882
 
رد: مصر بين الواقع و الخيال ( موضوع للمناقشه ) ؟؟

انا اعلم تماما عما اتكلم
هل تعتقد انه سيلعن عن ان السد دمر وهو مشروع حيوى لاثيوبيا ان الاخبار تأتى بالتدريج مثل هذا الخبر

Eyewitnesses reported to Ethiopian Review yesterday that Tekeze River in northern Ethiopia has flooded, raising suspicion that the recently completed hydro-power dam may have sustained damage. Some speculate that the Woyanne regime flooded the river to restrict movement in the area, which has seen intensified movements by Ethiopian resistance groups who are fighting against the brutal regime.
Normally, until the month of July, Tekeze's water level is low. In the past few days, unexpectedly the river flooded causing some people who tried to cross it to drown.
The Woyanne regime is not willing to give out any information about the flood.
The Tekeze hydro-power project was inaugurated on November 14, 2009. It has the capacity to generate 300 MW electric power and was constructed at a cost of 3.9 billion birr. The project took seven year to complete.
In late January, the Gilgel Gibe hydro-power dam in southern Ethiopia stopped power generation when a part of its 26-kilometer tunnel
http://www.ethiopianreview.com/content/27119

اما افحتمك او لم افحمك فلا تقلق فليس كل ما يعلم يقال وكل شىء بوقته يظهر ففقط انا اظهر ما اريدة فقط
 
رد: مصر بين الواقع و الخيال ( موضوع للمناقشه ) ؟؟

انا اعلم تماما عما اتكلم
هل تعتقد انه سيلعن عن ان السد دمر وهو مشروع حيوى لاثيوبيا ان الاخبار تأتى بالتدريج مثل هذا الخبر

eyewitnesses reported to ethiopian review yesterday that tekeze river in northern ethiopia has flooded, raising suspicion that the recently completed hydro-power dam may have sustained damage. Some speculate that the woyanne regime flooded the river to restrict movement in the area, which has seen intensified movements by ethiopian resistance groups who are fighting against the brutal regime.
normally, until the month of july, tekeze's water level is low. In the past few days, unexpectedly the river flooded causing some people who tried to cross it to drown.
the woyanne regime is not willing to give out any information about the flood.
the tekeze hydro-power project was inaugurated on november 14, 2009. It has the capacity to generate 300 mw electric power and was constructed at a cost of 3.9 billion birr. The project took seven year to complete.
in late january, the gilgel gibe hydro-power dam in southern ethiopia stopped power generation when a part of its 26-kilometer tunnel
http://www.ethiopianreview.com/content/27119

اما افحتمك او لم افحمك فلا تقلق فليس كل ما يعلم يقال وكل شىء بوقته يظهر ففقط انا اظهر ما اريدة فقط

عذرا اخى فانا ضعيف فى اللغه الانجليزيه فما فهمته هو وجود حركه فى منطقة السد وقتال مع شئ ما فهل تتفضل وتترجم الفقره ولو باختصار والرجاء توضيح نقطة هل السد دمر بفعل العوامل الطبيعيه ام بتدخل بشرى ما....هذا على فرض ان ذلك لم يرد فى الفقره عاليه وشكرا مقدما
 
رد: مصر بين الواقع و الخيال ( موضوع للمناقشه ) ؟؟

ماشي بص يا سيدي هأتكلم معاك من وجهة نظري اولا بالنسبة لي الانهيارة الاقتصادي ده غير صحيح الدخل القومي المصري توجد ارقام تقول انه يتخطي 300 مليار وده رقم لا بأس به بالنسبة لي افريقيا والشرق الاوسط (لا امل للمقارنة مع الدول الاوربية ) بالنسبة لي الوضع السكري او وضع الجيش صحيح الجيش فيه وسطة بشكل كبير وفيه سرقة ولكن يوجد ايضا شخصيات شريفة ومحترمة جدااااااااااااااااااا داخل الجيش المصري وده شئ انا رأيته بعيني مش هاقولك بيحاربوا الفساد والوطن والكلام ده ولكن هاقولك انه فعلا بيحاولو يراعوا الله في عملهم بقدر المستطار وانهم بيجوا علي صحتهم الشخصية بشكل كبييييير فقد لي ارضاء الله وتحليل الاموال الي بيخدوها والي هي طبعااا مبالغ كبيييييرة مش هاقول لا ولكن فعلا يستحقوها عن جدارة بالنسبة لي نقطة التسليح واغلب الاسلحة قديمة لا اعلم عن اي جيش تتحدث احنا بنوشف بعينا الاسلحة المصرية في المناورات وبراجم طلائع النصر وحفلات الخرج وتظهر الاسلحة القديمة مع الحديثة ايضااا جايز الي بيقول كدا بيتكلم عن تجهيز المشاة العادية وهم بالفعل تجهيزهم وتسليحهم مقارنة بدول اخري مجاورة سئ ولكن في خطة لي تطوير المشاة سلاح وتجهيز (خوذات الكليفار دروع مضادة للرصاص استبدال البنادق المعادي القديمة بأخري احدث) ولكن لا تنسي ان عدد المشاة او الجنود عامة في الجيش المصري اكبر من اي جيش اخر في المنطقة لذا فتلك العملية هتأخذ وقت وراجع او اتفرج علي فيديوهات الجيش المصري في المناورات والتدريبات هتلاحظ انتشار الخوذة الكليفار بين فروع الجيش وايضا الدروع المضادة للرصاص المجندين من اصدقائك واصدقائي نعم بيشوفوا ايام صعبة وذل قهر ولكن يا اخي هؤلاء جنود واذا لم يتحملوا ايام صعبة تدريبا او وقفة ساعتين في الشمس فكيف هيتحملوا قذائف الفسفور الابيض من العدو في الحرب والتعذيب في لا قدر الله الاسر وبعدين اذا كان اصدقائك بيشتكوا من القهر والظلم في مراكز الجنيد حسب كلامهم اطلب منهم يسألوا الي بيحصل لي الجنود اثناء تدريبا فرقة الصاعقة او السيل (تدريبات غير ادامية) بالنسبة لي الوضع السياسي فنصيحة مني ما تتفرجش علي قناة الزريبة الشهيرة بالجزيرة لانها القناة الوحيدة المبنية علي سب مصر والنظام في مصر وتناسوا تماما القاعدة الموجودة في ارضهم بالنسبة لي موضوع المعابر فكلام الجزيرة غير صحيح المصابين كانو يدخلون وسيارات الاسعاف المصرية دخل القطاع وهناك اكتر من طبيب مصري اصيب وموضوع الانفاق الجميع عارف انه بعلم السلطات المصرية وانهم يسمحون بدخول الاسلحة عبرها وباقي البضائع فبغير المعقول وجود مئات الانفاق علي شريط حدودي ليس بالكبير ولا تعلم حرس الحدود عنه شئ (ياراجل دول لو موقفين كتاكيت كانو اخدو بالهم) النسبة لي موضوع الوزراء والفساد فده امر مسلم بيه ومعروف وجود فساااااااااااد كبيرة في المنظومة وسرقة ...الخ (ربنا يجعل كلامنا خفيف عليهم) بس برضه والله العظيم في ناس شرفاء وبيشتغلوا بجد بعيد عن الكلام ده وعموما السرقة مش في بلدنا بس موجودة في كل دول العالم وبشكل سافر اكتر من كدا ايضاااااا واكبر دليل امريكا ولكن الفرق انهم هناك يسرقوا بأحترافية اكبررر وبيقدرو يخفوا عمليات السرقة والنهب

معاك حق فى كل الكلام ده الراىء المظبوط واتمنى عدم رؤية الامور من منظور اسود
 
رد: مصر بين الواقع و الخيال ( موضوع للمناقشه ) ؟؟

يا أخ mr.x الخبر الأول تحدث عن انهيار النفق المؤدى لمحطة Gilgel Gibe 2 ( بعيده تماما عن سد تيكيزى ) و الخبر الثانى يتحدث عن شاهد عيان رأى نهر تيكيزى يفيض مما يثير الشكوك فى احتمال اصابة السد بتلفيات .. شكوك و احتمال و تلفيات .. قارن بينهما و بين كلمة انهيار السد ..من يقرأ الخبر الثانى نفسه بمزيد من التمعن سيقول بأن السد لم ينهار و إلا لما ذكر شاهد العيان أن النهر فاض , كان الأدعى أن يقول أن السد انهار ( لو حدث لا قدر الله و انهار السد العالى هل سنقول النيل فاض أم سنقول السد انهار ) , و لم يكن الخبر ليقول بأن هناك احتمال فى حدوث تلفيات كان ليقول بأن هناك انهيار و هذا شئ لا يخفى ( تلفيات معناها أن بدن السد سليم لكن فيه بعض الأضرار ) .. انه سد , إذا انهار سيعرف أنه انهار .. أنا لا أعرف الوضع الداخلى فى أثيوبيا ديموقراطيا لكن بفرض أن الرجل طاغيه فلن يخفى على شعبه أن سدا انهار و ستلم الصحف - أى صحف - بالخبر و ستنشره

لو كان لديك شيئا أظهره
 
الحالة
مغلق و غير مفتوح للمزيد من الردود.
عودة
أعلى